Not much to report - except that the support walls have been poured (and I can't believe I missed it --but I am told that the driver/operator of the concrete pumper truck was a woman!!) Girl Power!!
So- now they have removed the forms...and are filling in with some dirt - then they will compact it...fill some more - compact some more.....fill..compact...fill...compact... and the final layer will be crushed stone. That's alot of shoveling, lol.
After that is done - then the slab will be poured.
Here is a pic of the support walls..... the long rebar will be repositioned to a horizontal position and will become part of the slab. The smaller bolts that are sticking out of the top of the wall is what the framing will attach to.

Oh yeah - and the plumbers are here scoping out what they need to get started on!
Here is what's coming our way!!

Give me a call for more info on these great downtown condo units.
Pre-construction prices won't last!!
2 Bedroom/2 Bath: $429,000
3 Bedroom/2 Bath: $489,000
You couldn't ask for a better location than this! Perfectly Downtown :) If you are thinking about a 'Southern get-away' ---- this would be ideal! A place to get away to -- a place for family and friends to get-away to..... You could even make a few bucks and rent it out for Master's week (next year... (if you weren't coming down for the tourny)
Give a call! Be sure to let me know you saw my blog :) Jane Page and I are looking forward to helping you.